LIHIR GOLD MINE - TAILING THICKENER Lihir Gold Mine - Tailing Thickener
General Scope of Work :  Supply of steel raw material +/- 1500 Tons,  Supply of shop construction drawings, Fabrication of steel structure and precision plateworks and trial assembled as a precision giant equipment, NDT & QA/QC Inspection, and MDR (manufacturing data report), Surface protection external surface, Rubber Lining and packing for sea transport
Client : FLSMIDTH MINERAL – GOSFORD NSW AUSTRALIA for End User LIHIIR GOLD MINE ................. More
|
Bolted Thickener - Hope Downs 4 Mining, Pilbarra WA (Rio Tinto)
Again, After successful with similar Bolted Thickener at Cadia Mine, Flsmidth Mineral Australia assigned Lintech to do complete supply, fabrication, preassembly, packing and FOB one complete set for final destination Pilbara Mine (WA) – Rio Tinto operation.
Lintech is committed to continuosly deliver high quality product, Australian standard quality at Indonesia’s competitive price and excellent services.
Client : FLSmidth Pty Ltd ................. More
|
Lintech Seaside Facility Project
Oil&Gas, Marine, Mining & Industrial Engineering - Fabrication - Construction
LINTECH SEASIDE FACILITY PROJECT – PIPING, STRUCTURE, PONTOON, TANK, SILO,
MECHANICAL WORKS WITH SIZE AFTER ASSEMBLE BIGGER THAN 6MX6MX6M, It will
require to be manufactured and assembled at Lintech Sea Side Facility. This New Sea Side facility is
being supported by Existing 20,000sqm Lintech Surabaya’s Steel ................. More
|
Martabe Mining Plant Structure
Lintech has completed several steps of bidding and
technical clarifications to finally awarded this capital project.
Experienced staff and workers, Quality control and timely experiences
have put this project in the correct hand of Lintech for trouble free
execution up to completion, delivery Free on Truck on site Martabe.
Congratulation for the End User for using the
quality products for their very infrastructure that being made at
Lintech Shops.
End User      : PT.AGINCOURT RESOURCES – Martabe Gold Mine
Fabricator     : Lintech Surabaya Shop and Lintech Seaside Facility (LSF)
Delivery Time :
No
Building
Due Date
1
Grinding Area
19-Mei-11
2
Leach ................. More
|
SAIPEM - Karimun Island Diesel Storage Tank
 SAIPEM – KARIMUN ISLAND DIESEL STORAGE TANK
Client                     : PT.SAIPEM INDONESIA (ENI)
Completion Date  : TARGET September 2010
General Scope of Work :
- DIMENSION/CAPACITY:
2 Storage tank : Dia. 9000mm x Height 9000mm/575.000 liters
1 Storage Tank : Dia. 4500mm x Height 4000mm/60.000 liters
- Supply of steel raw material,
- Supply of shop construction drawings,
- Fabrication Assembly,
- NDT & QA/QC Inspection,
- Surface protection external surface, and packing for sea transport
- Insurance and SEA TRANSPORT delivery from Lintech
Seaside Facility to SAIPEM’s JETTY at KARIMUN ISLAND- RIAU
- KARIMUN Site ................. More
|
Lihir Thickener succesfully shipped from LSF
Again, LSF successfully complete 2 Ea x 45m diameter thickeners for Lihir Gold Limited, Lihir island, Papua Newguinea. The shipment utilize barge 300ft (5000DWT) at LSF wharf. Along with the approval of the port operation, LSF is now legally able to import and export project material from and to regional Indonesia's island or overseas. We work closely with custom department and local port authority for fast and effvicient services at ................. More
|